Saturday, March 15, 2014

Meeting Minutes 3/15

Meeting Minutes 8/15

Aim to put together first iteration of yo-yo the middle of the week after spring break
- this means try to have molds machined before spring break, and injection mold ~5 parts during or immediately after spring break
- we should try to see how we have to adjust the molds in order to make our yo-yo run before the final process optimization, which is due in the 4/18 deliverable.  This requires a 6 batch run of 6-10 parts each
- there will be more meeting times during this week in order to get process optimization nailed down
- look at Gantt chart!

**WEDNESDAY MORNING IS AVAILABLE FOR US TO MACHINE DURING LAB**

Updates on Machining and First optimization Run
Jess & Kaitlyn - mold made, thermoforming next week
Helena - making mold on friday, aiming to injection mold friday or monday of spring break
Sarah & Isabella - talking to David 9-10 am monday morning to discuss final design considerations, trying to machine on monday, hopefully making parts during wednesday lab
Colette & Kristyn - need to consult kristyn about time

Need to order shims & rivets in order to put yo-yo together.
- Kaitlyn- order rivets (linked here)
- Helena - order shims → the only dimensional change we will need to order shims will probably be the ID of the body
-thermoform window cut to 2.25” on outside (will use 2.29” punch and die set then)
- shim stock remains same as one sent to team
- body - getting rid of step down and making it flat
- add step to inner retainer diameter to hold sandwiched parts in place